TCO InspectionDate Called In:
08-30-2021
Date Inspect On:
09-01-2021 AM
PM
Park City
445 Marsac Ave
Park City, UT 84060
PHONE # (435) 615-5100
dave.thacker@parkcity.org
COMPLIANCE INSPECTION REPORT
OWNER NAME: CRG Development OWNER email: paladinparkcity@aol.com
OWNER/BUILDER: Big D Construction Requested by: Natalia Earl
ADDRESS: 1271 Lowell Ave, KINGS CROWN RE-SUBDIVISION , Phase 1 ,
Lot # 2 , Park City Phone #: (801) 573-
PERMIT #: 19-553 Email: natalia.earl@big-d.com
Description: Building Permit for Phase 1 of the KC Condo Buildings B & C Permit Type: Commercial- New
INSPECTION OF ITEMS LISTED BELOW:
Building Inspections
CONDITION OF INSPECTION:
PASS PARTIAL PASS 36 NO PASS
ITEMIZED AND DESCRIBED AS FOLLOWS:
Final
Building Final Inpsection:
1. Unit B101 - Approved for temporary occupancy
2. Unit B102 - Approved for temporary occupancy
3. Unit B103 - Approved for temporary occupancy
4. Unit B201 - Approved for temporary occupancy
5. Unit B202 - Approved for temporary occupancy
6. Unit B301 - Approved for temporary occupancy
7. Unit B302 - Approved for temporary occupancy
8. Unit B401 - terminate electrical for hot tub in approved box
- install sink at powder room
9. Pool Area - Approved
10. Lounge and Amenity Areas - Sinks in bathroom not complete
- Complete electrical cover plates.
DATE & TIME SIGNATURE OF DESIGNATED COMPLIANCE INSPECTOR
1. Pool Inspection 2. Limits of Disturbance (LOD)
Passed: 12/26/19
3. Temp Power
Not Ready: 01/13/20
4. Footings/Piers
Partial Pass: 05/17/21
5. Foundation
Partial Pass: 09/29/20
6. Grout/Bond Beam
Partial Pass: 09/15/20
7. Und. Plumbing
Partial Pass: 05/12/21
8. Und. Mechanical
Partial Pass: 06/24/21
9. Und. Electrical
Partial Pass: 06/24/21
10. Und. Gas Line 11. Slab/Holddowns
Partial Pass: 01/20/21
12. Slab on Grade
Partial Pass: 08/10/20
13. Shear Wall
Partial Pass: 12/02/20
14. Ext. Moisture Barrier 15. Roof Sheathing/Framing
Partial Pass: 11/19/20
16. Roof Covering
17. Rough Framing
Partial Pass: 06/14/21
18. Rough Electrical
Partial Pass: 04/23/21
19. Rough Mechanical
Partial Pass: 04/23/21
20. Rough Plumbing
Partial Pass: 04/23/21
21. Fire Wall
Passed: 07/08/21
22. Masonry/Stone Veneer
Partial Pass: 05/17/21
23. Stucco/Ext. Siding 24. Gas Line/Meter Set
Passed: 06/03/21
25. Insulation
Partial Pass: 06/09/21
26. Sheetrock
Partial Pass: 06/23/21
27. Shower Pan
Partial Pass: 07/02/21
28. Fire Sprinkler
Partial Pass: 12/30/20
29. Power to Panel
Passed: 03/02/21
30. Retaining Wall
Passed: 06/15/21
31. Fire Inspection 32. Final Electrical
33. Final Mechanical 34. Final Plumbing 35. Final Fire Inspection
Not Ready: 07/21/21
36. Final
Partial Pass: 09/03/21
37. Drive Approach 38. Grading 39. Landscape 40. Temp C/O
No Pass: 07/12/21
41. Final C/O