22-238 PreinspectionAPPROVALS DATE INFO
22-238 (C)
CONTACT INFORMATION
APPLICATION DETAILS
APPLICATION NUMBER:
This permit becomes null and void if work or construction authorized is not commenced within 180 days, or if
construction or work is suspended or abandoned for a period of 180 days at any time after work is commenced. I
here-by certify that I have read and examined this application and know the same to be true and correct. All
provisions of laws and ordinances governing this type of work will be compiled with whether specified herein or not
the granting of a permit does not presume to give authority to violate or cancel the provisions of any other state or
local law regulating construction or the performance of construction and that I make this statement under penalty of
perjury.
Park City
Building Permit Permit #:
Issue Date:
22-238 (C)
04/07/2022
Type of Improvement: Pre-inspection
Description:
Bldg. Address: 2651 LITTLE KATE RD
City: Park City State: UT Zip: 84060
Subdivision: Phase:
Block: Lot #: Parcel #:
Property Owner: CLOTFELTER SHARON GEORGENE
City: PARK CITY State: UT Zip: 84060
Permit Contact:
Email:
General Contractor: J&i remodeling corp
License #: P: (385) 227-4585
City: State: Zip:
Email: Coronadojose27@gmail.com
Electrical Contractor:
License #: P:
City: State: Zip:
Plumbing Contractor:
License #: P:
City: State: Zip:
Email:
Mechanical Contractor:
License #: P:
City: State: Zip:
Email:
$ Construction Valuation 0.00
$ Electrical Valuation 0.00
$ Plumbing Valuation 0.00
$ Mechanical Valuation 0.00
PERMIT FEES
Inspection - Additional Services $ 0.00
Total Fees:$ 0.00
Setbacks Front:Rear:Left:Right:
Min.
Actual:
Applicant Name:
Signature of Builder/Authorized Agent or Owner:Date:
Application Approved By:Date:
Permit Issued By:Date:
Dave Thacker 04/07/2022
Receipt #:Date:
Date Called In:
04-07-2022
Date Inspect On:
04-11-2022 AM
PM
Park City
445 Marsac Ave
Park City, UT 84060
PHONE # (435) 615-5100
inspections@parkcity.org
COMPLIANCE INSPECTION REPORT
OWNER NAME: CLOTFELTER SHARON GEORGENE OWNER email:
OWNER/BUILDER: J&i remodeling corp Requested by:
ADDRESS: 2651 LITTLE KATE RD , Park City Phone #:
PERMIT #: 22-238 Email:
Inspection Notes: This is for a true scope of work.
INSPECTION OF ITEMS LISTED BELOW:
Building Inspections
CONDITION OF INSPECTION:
PASS PARTIAL PASS NO PASS 2
ITEMIZED AND DESCRIBED AS FOLLOWS:
Pre-Inspection
Walk through to get scope of work.
DATE & TIME SIGNATURE OF DESIGNATED COMPLIANCE INSPECTOR
1. pre-inspection 2. Pre-Inspection
No Pass: 04/11/22
3. Limits of Disturbance (LOD)4. Temp Power
5. Footings/Piers 6. Foundation 7. Grout/Bond Beam 8. Und. Plumbing
9. Und. Mechanical 10. Und. Electrical 11. Und. Gas Line 12. Slab/Holddowns
13. Slab on Grade 14. Shear Wall 15. Ext. Moisture Barrier 16. Roof Sheathing/Framing
17. Roof Covering 18. Rough Framing 19. Rough Electrical 20. Rough Mechanical
21. Rough Plumbing 22. Fire Wall 23. Masonry/Stone Veneer 24. Stucco/Ext. Siding
25. Gas Line/Meter Set 26. Insulation 27. Sheetrock 28. Shower Pan
29. Fire Sprinkler 30. Power to Panel 31. Retaining Wall 32. Fire Inspection
33. Final Electrical 34. Final Mechanical 35. Final Plumbing 36. Final Fire Inspection
37. Final 38. Drive Approach 39. Grading 40. Landscape
41. Solar Panel 42. Final Fire Inspection 43. Final Inspection (Building)44. Final Inspection (Planning)
45. Final Inspection (Engineering)46. Temp C/O 47. Final C/O 48. Stop Work Notice
2022-04-11 10:55:45 Bendy Olsen
Date Called In:
04-07-2022
Date Inspect On:
04-11-2022 AM
PM
Park City
445 Marsac Ave
Park City, UT 84060
PHONE # (435) 615-5100
brittney.buchanan@parkcity.org
COMPLIANCE INSPECTION REPORT
OWNER NAME: CLOTFELTER SHARON GEORGENE OWNER email:
OWNER/BUILDER: J&i remodeling corp Requested by:
ADDRESS: 2651 LITTLE KATE RD , Park City Phone #:
PERMIT #: 22-238 Email:
Inspection Notes: True scope of work
INSPECTION OF ITEMS LISTED BELOW:
Building Inspections
CONDITION OF INSPECTION:
PASS 2 PARTIAL PASS NO PASS
ITEMIZED AND DESCRIBED AS FOLLOWS:
Pre-Inspection
I attended a site visit to determine full scope with Bendy Olsen and Ben Henrie. See Bendy's inspection - 04/11/2022
DATE & TIME SIGNATURE OF DESIGNATED COMPLIANCE INSPECTOR
1. pre-inspection 2. Pre-Inspection - re
Passed: 04/11/22
3. Limits of Disturbance (LOD)4. Temp Power
5. Footings/Piers 6. Foundation 7. Grout/Bond Beam 8. Und. Plumbing
9. Und. Mechanical 10. Und. Electrical 11. Und. Gas Line 12. Slab/Holddowns
13. Slab on Grade 14. Shear Wall 15. Ext. Moisture Barrier 16. Roof Sheathing/Framing
17. Roof Covering 18. Rough Framing 19. Rough Electrical 20. Rough Mechanical
21. Rough Plumbing 22. Fire Wall 23. Masonry/Stone Veneer 24. Stucco/Ext. Siding
25. Gas Line/Meter Set 26. Insulation 27. Sheetrock 28. Shower Pan
29. Fire Sprinkler 30. Power to Panel 31. Retaining Wall 32. Fire Inspection
33. Final Electrical 34. Final Mechanical 35. Final Plumbing 36. Final Fire Inspection
37. Final 38. Drive Approach 39. Grading 40. Landscape
41. Solar Panel 42. Final Fire Inspection 43. Final Inspection (Building)44. Final Inspection (Planning)
45. Final Inspection (Engineering)46. Temp C/O 47. Final C/O 48. Stop Work Notice
2022-04-11 12:45:11 Brittney Buchanan
Last Inspection Completed: Pre-Inspection By: Brittney Buchanan
Current Status: archived Date: 04/07/2022
Building Inspections
1. pre-inspection
-
2. Pre-Inspection
Passed: 04/11/22
3. Limits of Disturbance (LOD)
-
4. Temp Power
-
5. Footings/Piers
-
6. Foundation
-
7. Grout/Bond Beam
-
8. Und. Plumbing
-
9. Und. Mechanical
-
10. Und. Electrical
-
11. Und. Gas Line
-
12. Slab/Holddowns
-
13. Slab on Grade
-
14. Shear Wall
-
15. Ext. Moisture Barrier
-
16. Roof Sheathing/Framing
-
17. Roof Covering
-
18. Rough Framing
-
19. Rough Electrical
-
20. Rough Mechanical
-
21. Rough Plumbing
-
22. Fire Wall
-
23. Masonry/Stone Veneer
-
24. Stucco/Ext. Siding
-
25. Gas Line/Meter Set
-
26. Insulation
-
27. Sheetrock
-
28. Shower Pan
-
29. Fire Sprinkler
-
30. Power to Panel
-
31. Retaining Wall
-
32. Fire Inspection
-
33. Final Electrical
-
34. Final Mechanical
-
35. Final Plumbing
-
36. Final Fire Inspection
-
37. Final
-
38. Drive Approach
-
39. Grading
-
40. Landscape
-
41. Solar Panel
-
42. Final Fire Inspection
-
43. Final Inspection (Building)
-
44. Final Inspection (Planning)
-
45. Final Inspection (Engineering)
-
46. Temp C/O
-
47. Final C/O
-
48. Stop Work Notice
-
Permit History
Notes
Attachments
J&i remodeling corp
Permit #: 22-238 (C) / Lot / / 2651 LITTLE KATE RD
Created By: Crystal Kaufman
Issued By: Crystal Kaufman
Closed By: Crystal Kaufman 22-238 (C)
04/07/22 Site Plan 04/07/22 Plans-interior